Monday, 5 October 2015

Jubilee bridge risk assessment



RISK ASSESSMENT FORM

 

Shoot date

Production Title

Page            of

17/10/15
JEALOUS TYPE
 

Producer

           SUMAYA

 

 


                                                                               

Location:
Jubilee bridge
Address: Hungerford Bridge and Golden Jubilee Bridges


RATINGS:

  1. each risks severity on scale from Negligable (N), Low risk (L), Moderate risk (M), Severe (S), Very severe (V)
  2. each risks likelihood on scale from Very unlikely (VU), Unlikely (U), Possible (P), Likely (L), Very likely (VL)
  3. risk factor from the table overleaf.

Hazard

Present?
Severity
Likelihood
Risk Factor
1
Alcohol/drugs
NO
2
Animals/insects
NO
3
Audiences
NO
4
Camera cable/grip equipment
NO
5
Confined spaces
NO
6
Derelict buildings/dangerous structures
NO
7
Electricity/gas (other than normal supplies)
NO
8
Fatigue/long hours
NO
9
Fire/flammable materials
NO
10
Hazardous substances
NO
11
Heat/Cold/extreme weather
YES
M
P
3
12
Laser/strobe effects
NO
13
Machinery/industrial/ crane/hoist
NO
14
Materials - glass, non-fire retardant set materials
NO
15
Night operation
NO
16
Noise – high sound levels
NO
17
Non standard manual handling
NO
18
Public/crowds
YES
M
P
3
19
Radiation
NO
20
Scaffold/Rostra
NO
21
Smoking on set
NO
22
Special effects/explosives
NO
23
Special needs (elderly, disabled, inexperienced)
NO
24
Specialised rescue/first aid
NO
25
Stunts, dangerous activities
NO
26
Tall scenery/suspended ceilings
NO
27
Vehicles/speed
NO
28
Water/proximity to water
NO
29
Weapons
NO
30
Working at heights
NO
31
Working overseas
NO
32
Other risks
NO


Calculate the Risk Factor:

Very Unlikely

Unlikely
Possible
Likely
Very Likely
Very severe
3
4
4
5
5
Severe
2
3
3
3
5
Moderate
2
2
3
3
3
Low
1
2
2
3
3
Negligible
1
1
2
2
3


Decide the action to take:

5
Very severe
Take immediate action
4
Severe
High priority
3
Moderate Risk
Programme for action
2
Low Risk
Action may be required
1
Negligible
Probably acceptable


Then list each risk identified


Hazard no:
1
Risk Factor (1-5):
2
Description
Heat/Cold/extreme weather
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
C,O
Action to take
DRESS WARM
Person/company responsible for action
PRODUCER
To be completed at agreed later date
Exposed person(s) informed? (y/n)
y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
Y


Hazard no:
2
Risk Factor (1-5):
2
Description
Public/crowds
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
C.O
Action to take
FILM AWAY FROM PEOPLE
Person/company responsible for action
PRODUCER
To be completed at agreed later date
Exposed person(s) informed? (y/n)
y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
Y
Hazard no:
Risk Factor (1-5):
Description
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
Action to take
Person/company responsible for action
producer
To be completed at agreed later date
Exposed person(s) informed? (y/n)
Y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
y


Hazard no:
Risk Factor (1-5):
Description
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
Action to take
Person/company responsible for action
To be completed at agreed later date
Exposed person(s) informed? (y/n)
y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
Y


Hazard no:
Risk Factor (1-5):
Description
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
Action to take
Person/company responsible for action
To be completed at agreed later date
Exposed person(s) informed? (y/n)
y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
Y


Hazard no:
Risk Factor (1-5):
Description
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
Action to take
Person/company responsible for action
To be completed at agreed later date
Exposed person(s) informed? (y/n)
Y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
y


Hazard no:
Risk Factor (1-5):
Description
Person(s) exposed (detail if cast/crew (C), outside company (O) or public (P) )
Action to take
Person/company responsible for action
To be completed at agreed later date
Exposed person(s) informed? (y/n)
y
Agreed action taken? (y/n)
y
Risk removed? (y/n)
Y



Completed by:  Maraam            Position: Producer


Signature                                                                      Date:5/10/15